How do you link two or more tasks?

There are several link options. Select two or more tasks, click on the “Link” menu and choose the appropriate linking option. The link icon on the toolbar assigns Finish-to-Start linking.

If two tasks need to be linked to the same Predecessor, you can either choose each pairing independently, and then choose the appropriate Link option; or, you can copy the name of the predecessor (Ctrl C) and paste (Ctrl V) the task name in the “Predecessor” column of the appropriate task.