Why can’t I change the dates on Child Tasks?

If you have a set of tasks with a Parent-Child relationship and the Parent task is linked to a Predecessor, the child tasks will be constrained and you will not be able to change the dates. Rather than linking to the Parent task, link to the first Child task in the set in order to avoid this issue.